1. |
What is the primary material requirement for the bridge superstructure according to the design criteria? |
|
|
Concrete |
|
|
Structural steel |
|
|
Fracture critical members |
|
|
Non-redundant materials |
2. |
What is the purpose of an independent peer review for a Category 2 bridge according to FDOT in Florida? |
|
|
To verify the original work of the EOR |
|
|
To check the EOR’s plans and calculations |
|
|
Both of the above |
3. |
What type of element is used to model the steel post-tensioning tendons in a numerical simulation of a post-tensioned member? |
|
|
A uniaxial compression-only element |
|
|
A uniaxial tension-compression element |
4. |
How is the real bonding condition between the concrete and steel post-tensioning tendons simulated in the numerical simulation?
|
|
|
By using an un-bonded formulation |
|
|
By using a triaxial formulation |
|
|
By using a bonded formulation |
5. |
Industry considers redundancy a critical factor in structural design.
|
|
|
True |
|
|
False |
6. |
Which of the following best describes the main span structure of the bridge? |
|
|
Redundant |
|
|
Determinate and redundant |
|
|
Determinate and non-redundant |
|
|
Indeterminate and non-redundant |
7. |
What was the recommendation made by TY Lin in the design criteria for the FIU bridge structure? |
|
|
Use of non-redundant, fracture critical members |
|
|
Concrete superstructure |
|
|
Steel superstructure with concrete walking surface |
|
|
Avoidance of non-redundant structures |
8. |
What was the cause of the cracks on the bridge during construction stage III? |
|
|
Poor maintenance |
|
|
Insufficient materials |
|
|
Deficient structural design |
|
|
Incorrect construction techniques |
9. |
Figure below shows the construction joint detail at deck.
|
|
|
True |
|
|
False |
10. |
The dotted lines in this figure belowdepicts what?
 |
|
|
Truss of the bridge |
|
|
Potential line of crack |
11. |
What did the EOR acknowledge during the meeting with project participants about the cracks in the bridge? |
|
|
The cracks were not a safety concern |
|
|
The EOR had a solution to the cracks |
|
|
The cracks were not growing in size |
|
|
The EOR did not know why the cracks were occurring |
12. |
Why was SW 8th Street closed immediately after the cracks on the bridge were found? |
|
|
Due to safety concerns |
|
|
To reduce the traffic |
|
|
For maintenance work |
|
|
To increase the bridge’s longevity |
13. |
What was the role of BPA in the construction project of the bridge? |
|
|
To provide construction materials |
|
|
To design the bridge |
|
|
To oversee construction and inspect the bridge |
|
|
To maintain the bridge |
14. |
Why did MCM defer to the decision of EOR in regards to the cracks in the bridge? |
|
|
MCM lacked knowledge of the magnitude of the cracks. |
|
|
MCM did not have any experience in concrete structures |
|
|
MCM was not informed of the growing size of the cracks |
|
|
MCM trusted the EOR’s judgement |
15. |
Was the design-build contractor, MCM, aware that the cracks were growing in size before the collapse of the bridge? |
|
|
True |
|
|
False |
|